-STREET LIGHT PROJECT- KAMPUNG SELAMAT, 13300 TASEK GELUGOR, P.PINANG. 'KERJA-KERJA MEMASANG LAMPU JALAN DI PERSIMPANGAN JALAN KAMPONG SELAMAT, DAERAH SEBERANG PERAI UTARA, PULAU PINANG' CONTRACTORMABA ELECTRICAL ENGINEERINGNO.16, LORONG PERDA UTAMA 2, BANDAR PERDA, 13700 BUKIT MERTAJAM, PULAU PINANG CONTRACT AMOUNTRM 333,960.00 DATE OF SITE OWNERSHIP29th JULY 2019 END DATE17th NOVEMBER 2019 COMPLETED PROJECT REFERENCES Continuity Testing Of Resistance To Earth & Testing In Last Column Corrugated Pipe 150mm Installation G.I Pipe 150mm Installation Cable Pit 600mm x 600mm x 900mm Installation Street Lighting Pillars Installation Street Light Cable Installation Wiring Inside the Pillar & Earthing System Pole Installation Feeder Pillar & TNB Meter Installation Metal Barricades Installation Cable Pit Hood Holder Installation & Water Hole Inside Cable Pit Sticker Installation & Report Books (MBSP) STREET LIGHT EQUIPMENT GOODS